Buffer Management principles work very well for procurement of short transportation lead-time items. However, additional controls are often needed for items where transportation lead-time forms a significant component of replenishment lead-time. A review of the buffer management principles would be instructive to understand this point.
Buffer Management principles
Let us look at the four Buffer Management principles under the Theory of Constraints.
1. Initial Buffer between any two links in the supply chain = Maximum forecasted consumption within the reliable replenishment lead-time.
- Replenishment lead-time = Order lead-time + Production lead-time + Transportation lead-time
- Order lead-time = Time between two consecutive orders or the time between the consumption of an item and placement of order.
- Production lead-time = Time from the placement of order to the time that the supplier dispatches the order
- Transportation lead-time = Time between the dispatch from supplier and the receipt of items in your warehouse.
2. A buffer is divided into three equal zones demarcated by the colors red, yellow and green in that order starting from the bottom.
3. Follow up and expedite the items when stocks are in the red zone.
4. The buffer levels would have to be altered regularly because lead-time and consumption are prone to variability. Dynamic Buffer Management rule states that if the physical stocks of the purchased items in your warehouse are continuously in the red zone, there is always a threat that items would be stocked out and hence the buffer would need to be increased. However, if the stock is consistently in green, thereby indicating a high a stock, the buffer levels would have to be reduced. Enough evidence exists that an increase or reduction by a complete zone is enough to ensure availability of stocks without high inventories or excessive management attention.
The challenge
Shifting of supply base from the consumption location is increasing the transportation lead-times considerably. A typical case of procuring items by an Indian manufacturer from a Chinese supplier is illustrated below:
Order lead-time = 4 weeks
Production lead-time = 4 weeks
Transportation lead-time (On high seas) = 4 weeks
The resultant physical stocks in the warehouse in this case would be less than or equal to one-third of the buffer, i.e., the stock equivalent to the order lead-time. If the orders were to be expedited only after the stocks reached the red zone, it would be too late as the supplier would not have dispatched the items which would take another four weeks to reach the warehouse. The possibility of a delayed dispatch is high in this case since suppliers in China cater to a worldwide market and order size from Indian customers is comparatively very small. Hence resorting to action in the red zone is a sure-shot recipe for stock outs when the transportation lead-time is long.
The Solution
Since there cannot be any control on shipment time once the stocks are shipped, the point of control is prior to the shipment. There are two possible actions that can be taken to prevent stock outs:
1. Requesting the supplier to ship much faster than the standard Production lead-time of 4 weeks.
2. Use faster modes of transport such as air.
In other words, the control must be on the virtual buffer being the physical stocks and stocks in transit. The rules than are to be followed for preventing a stock out, therefore, are simple:
1. Start requesting supplier to ship before the virtual buffer comes into the yellow zone.
2. If the virtual buffer is in the red zone or nearing the red zone, chose a faster mode of freight.
Procurement managers are often assessed on material and transportation costs. Air freight is something they usually avoid. However in a majority of cases, air freight will be only a fraction of the money the company would make, had the items been available.